Lift erection work completed. One coat of white cement for all interior walls completed. Foyer flooring & granite work completed. Wall tailing for toilets completed. Floor tiling completed for G1, F1, F2, S1 & S2 flats. Kitchen shelf & cooking table in all flats except F2 completed. RWH & compound wall completed. Main gate fixed. First coat of Interior paint for F1, F2 & S2 is completed. |