Navin's CHELLAM - SoldOut
 
Front Elevation
Location
Flats Details
Site Plans
Specifications
Features

Payment Schedule

Project Status
Click to download E-Brochure

Click here to enlarge


Flat Area Availability

     FLOORS        
Area in sft
       Area in sft      
Ground
Car Park
Car Park
I
1116*
1105*
II
1116*
1105*
III
1116*
1105*
*One Covered Park
  Available    

Address: New # 18, Seethamma Extn., 2nd Cross Street, (opp. SIET college) Teynampet, Chennai-600 018.

Project Plans
 
Ground Floor Plan
   
Click here to enlarge

Typical First, Second & Third Floor Plan
   
Click here to enlarge


Specifications
 
Structure
:
R.C.C. Framed Structure.
Walls
:
Brick W ork in C.M using stock bricks or fly ash Cement blocks
Door Frames
:
Main Door in T.W. Other Doors in C.W.
Door Shutters
:
Imported Skin Main Door Shutters
Windows
:
C.W. with M .S. G rills and Glazed Shutters
Kitchen
:
Polished Granite Platform with Stainless Steel Sink,Ceramic Tiles Dadoing
Toilets
:
Ceramic Tiles Flooring, Glazed Tiles & Dadoing with Good Quality Sanitary Fittings (Jaguar or equivilant)
Flooring
:
Granite Flooring for Ground Floor lobby & staircase areas. Vitrified tiles flooring inside of flats.
Electricity
:
Three Phase Electric Supply with Concealed Copper Wiring, Circuit Breaker & Modular switches A.C. Point in Bedrooms
Finishing
:
Internal walls finished with wall patty and painted with emulsion paint. External walls finished with antifungal matt paint.
Doors & Windows
:
Enamel Paint.
Main Door
:
melamin Polish.
Water Supply Arrangements
:
Sump to receive Metro Water, Bore Well / Open Well for Tapping Ground Water.
Other Features
:
5 Passenger Lift of Reputed MakeAccess control with Video door phone. Pathway with interlocking pavers Plesant landscaping.


SCHEDULE OF PAYMENTS
 
Down payment at the time of Booking
:
20%
At the time of Registration of Land
:
25%
At Foundation Stage
:
15%
On Completion of Respective Roof Slab
:
15%
Upon Completion of Internal Plastering
:
15%
Laying of Flooring
:
5%
Before Handing Over
:
5%

EXTRA EXPENSES
 
Registration Charges.
Legal Fees, Documentation Charges & Incidental Expenses.
Sales Tax and Service Tax.
Service Connection Charges, Fees, Deposits and Incidental Expenses
for Electricity, Water Supply, Drainage and Cost of Rain Water
Harvesting System.

PROJECT STATUS
 
Chellam
:

All the  flats  flooring  completed, except one toilet’s wall & flooring.  2 coat putty for all  flats completed.  Common area flooring  completed.  Out side painting  completed. Doors & windows  fixing  completed. Compound wall (all side) BW  completed & plastering  under progress.  RWH  completed. 

    Status As on 31.12.07

CLICK HERE TO DOWNLOAD 166KB

"The details shown in this page are for the purpose of illustration only. The information contained herein is subject to change and cannot form part of an agreement or contract."